Replacing ageing 33kV cables beneath a railway, a motorway and a stream.

Project Overview

Two ageing oil-filled cables link Titahi Bay and Porirua substations. As the area grows, Wellington Electricity is replacing them with XLPE cables, and Omexom is delivering installation, jointing, terminations and commissioning.

The toughest section runs beneath KiwiRail tracks, State Highway 59 and Porirua Stream, where a mistake could flood the highway and railway. Consultants’ soil testing, including core drilling, is informing a design now being finalised with KiwiRail, NZTA and Porirua’s flood team.

Wellington Electricity’s civil contractors are already on site installing ducts. Specialist Auckland hauling crews will follow, starting late November, to limit disruption and clear busy shopping areas before mid-December.

With the crossing design and approvals agreed before any drilling begins, the project is well placed for safe delivery by 31 March 2027.

Project Information

Client: Wellington Electricity

Location: Titahi Bay to Porirua, Wellington

Project: Titahi Bay Subtransmission Cable Replacement

Duration: 2026 – March 2027 (Expected completion)

Sector: Electricity Distribution (33kV Subtransmission)

Status: Ongoing

Delivering Reliable Electricity Infrastructure Across New Zealand

From underground cable installation to complex electricity distribution upgrades, Omexom delivers integrated electrical infrastructure solutions that support New Zealand’s evolving energy needs.

Latest news